Project
Current position > Projects > Municipal project
Waste water treatment project in Longgui phase I Partial pipe net construction of the western part in Longgui
Release time:2015-06-12
Pipe laying, structure constructing, foundation treatment, broken roadsrepair and some other accessory engineering constructions related to sewer lineengineering are our duties. The contaminated area is about 200m2 andthe total length of the pipes is 20km in which 3km are under pipe-jackingconstructing and 17km are under open-cut construction. Open completion time: 2005.12 - 2011.6.14 Construction cost: 7797 Million yuan Awards:double priority site of the city in 2007
Address: Guangdong Province Guangzhou city Haizhuqu District South Island Road Xijiao 11 Street No. 12 TEL:020-84012668 FAX:020-84011360
Copyright © 2015 Guangdong Chang Hang Construction Engineering Co.,Ltd All Rights Reserved. 粤ICP备05138076号
Copyright © 2015 Guangdong Chang Hang Construction Engineering Co.,Ltd All Rights Reserved. 粤ICP备05138076号



