Waste water treatment project in Longgui phase I Partial pipe net construction of the western part in Longgui

Release time:2015-06-12

Pipe laying, structure constructing, foundation treatment, broken roadsrepair and some other accessory engineering constructions related to sewer lineengineering are our duties. The contaminated area is about 200m2 andthe total length of the pipes is 20km in which 3km are under pipe-jackingconstructing and 17km are under open-cut construction.

Open completion time: 2005.12 - 2011.6.14
Construction cost: 7797 Million yuan
Awards:double priority site of the city in 2007


 